Czech deal restores 639 MW to Aleppo thermal plant
Three idle units return to service in stages, lifting the plant's capacity to about 1,040 MW.

The Syrian Electricity Company has signed an agreement with Czech firm Energy Care to rehabilitate three generating units at the Aleppo thermal plant.
The three units have a combined capacity of 639 MW, under the agreement signed on Sunday, 15 November 2026, at the Energy Ministry building in Damascus.
The agreement was signed for the Syrian Electricity Company by Imad Abu Ali, director general of the Aleppo power plant, and for Energy Care by its representative in Syria, Haitham Eid.
The signing was attended by Energy Minister Mohammed Al-Bashir and the Czech Republic’s ambassador to Syria, Vitezslav Pivonka.
Al-Bashir said the agreement is a new step on the path to recovering Syria’s electricity sector.
Work will start once the site is logistically equipped with all machinery and equipment.
The agreement is part of the Energy Ministry’s plans to rehabilitate generating plants and raise their operational readiness.
Parties: The Syrian Electricity Company × Czech firm Energy Care.
Agreement value: $93 million.
Scope: Rehabilitation of units 2, 3 and 4 — 213 MW each.
Timeline: Unit 2 in 30 months, unit 3 in 18 months, unit 4 in 24 months — work runs in parallel.
Current capacity: About 400 MW (unit 5: 202 MW; unit 1: about 195 MW).
After rehabilitation: More than 600 MW fed into the grid, and total available generating capacity of about 1,040 MW (out of 1,065 MW design capacity).
Separate context
A $90 million concessional loan from the Saudi Fund for Development, announced on 4 November 2026, to rehabilitate generating units at the same plant — separate financing from the implementation contract, and no source links the two directly.

Read next: Saudi concessional loans of $403.6 million for Syria — $60 million to rehabilitate 10,000 housing units
Back to homepage