Magazine

Hama Cement Restarts Its Third Plant After Two Years of Shutdown

After two years of shutdown, Hama Cement's third plant has entered trial operation under a 25-year investment contract, with a plan to more than triple its output.

10 November 2026•2 min read•Construction & Investment Prime
Hama Cement Restarts Its Third Plant After Two Years of Shutdown
Hama Cement’s third plant after the completion of maintenance and rehabilitation works

Hama — 10 November 2026 | Reading time: 1 minute

Prepared by: Construction and Investment in Syria (CIP)

The third plant of the General Company for Cement and Building Materials “Hama Cement” has begun trial operation early this month, after maintenance and rehabilitation works carried out by the Iraqi company Al-Khala, a subsidiary of Nahdat Al-Mashriq Holding, under a 25-year investment contract.

Plant manager Eng. Abdul Basit Ahmed Abdul Muttalib said the plant had been out of production since 2024, in need of maintenance, rehabilitation and imported spare parts, and that current actual capacity is about 3,300 tonnes of clinker per day, in line with design capacity.

The plan targets raising output to 5,000 tonnes per day, then building a new plant with a capacity of 6,000 tonnes, bringing total capacity to about 11,000 tonnes of clinker per day, helping meet the needs of the construction and reconstruction sector and reduce imports.

The investment contract also covers rehabilitating the workforce and raising staff efficiency through specialised training courses keeping pace with the technology used, as part of restarting idle industrial facilities and supporting national production.

Prepared by: Construction and Investment in Syria (CIP) — All rights reserved

Read next: «Faz» signs investment contract to build three new mills and rehabilitate six mills in Syria
Back to homepage:

Follow Construction & Investment Prime
Subscribe to receive the latest articles, real estate and investment projects in Syria
Subscribe Now